JB Progress Billing – Billing Purchased and Installed Materials
Purpose: Update the Application for Payment report, showing purchased materials in Column F and installed materials in Column E.
Steps:
1. Record Purchased Materials
Create a bill and go to the Items SM/Tax tab.
Enter the Purchased Materials amount.
The SM Retg % and Retg Amount will default based on the JC Contract Item.
This will show the purchased materials in Column F (Materials Presently Stored) on the report.
2. Record Installed Materials
On a later bill, enter the Installed Amount (must be ≤ previous purchased amount).
SM Retg will default as negative; ensure the retainage percent matches the original purchase.
Go to the Items tab and enter the Installed amount in This Bill WC Amount.
This updates Column E (This Period in Place) on the report.
If other work is already recorded, add the Installed amount to include it in the total work complete.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article