IN Material Orders can be processed through Project Management (PM) or IN Material Order Entry.


1. IN Material Order Entry

  • Used to enter materials allocated to a Job

  • Posting the batch:

    • Updates JC committed costs

    • Allocates inventory units

  • Before confirmation:

    • Items can be edited or deleted by adding the order to a new batch

  • After items are confirmed:

    • Items can be edited, but not deleted

    • The material order cannot be deleted


2. IN Material Order Confirmation

  • Used to confirm receipt of materials

  • Confirmation:

    • Reduces JC committed costs

    • Reduces inventory

    • Updates JC detail and GL

  • Confirmed lines cannot be deleted

  • To undo, enter a reversing confirmation


3. IN Material Order Close

  • Closes the material order (even if not fully confirmed)

  • If units remain unconfirmed:

    • JC committed costs are relieved

    • Inventory allocations are removed

  • Closed orders can be reopened, but:

    • Committed costs and inventory allocations are not restored

    • A new material order is recommended for remaining units


4. IN Material Order Purge

  • Permanently removes closed material orders

  • Job Cost and Inventory history remain intact


Additional Option

  • You can copy a material order from
    IN Material Order Entry > File > Copy Material Order


Summary

  • Enter → Confirm → Close → Purge

  • Confirmations affect JC, Inventory, and GL

  • Closing removes remaining commitments

  • Purging removes order detail only, not financial history

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article