Set Up in JC Contract Master:
Go to JC > Programs > JC Contract Master.
Set Bill Type to B-Both.
Enter a retainage percentage.
You can set this for all items (Info tab) or individual items.
If changing from T&M to Both, you’ll get a prompt—click Yes to update all items or No to update only selected items.
Set Up in JB T&M Template:
Go to JB > Programs > JB T&M Template Setup for the contract’s template.
Create a Total Addon sequence below the source sequences that will have retainage.
Set Markup Option to R-Retainage.
No need to enter a markup rate (it uses the JC Contract Master rate).
On the Basis tab, click Initialize Basis of Addon to select which sequences retainage applies to.
Once bills are initialized, retainage will automatically be held based on these settings.
Releasing Retainage or Holdback on T&M Bills
Prepare Progress Bill:
Go to JB > Programs > JB Progress Billing.
Create a new bill with no amounts billed.
Enter + or N in the Bill Number field, then tab to enter Invoice number and Contract number, and Save.
Release Retainage:
Open JB Release Retainage. It should default to the bill just created.
If not, select the correct Bill Month & Bill Number.
Enter the amount or percentage to release and Save.
Optional:
You can release retainage on a bill that also has billed amounts if:
In JB Company Parameters, the box “Allow changes to Progress Bill data when both Progress and T&M exists” is checked.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article